Our Construction Team at St James Square on track and looking forward to completing demolition of level 7 roof and level 6 over the next few weeks in preparation for steelwork installation to ground floor and column strengthening throughout the building.
 

Photo above - putting the lid on our 26 St James Square project for Morgan Capital preparing for the major re-sculpting and extensions of the 3 top floors and core reconfiguration - some challenging structural alterations coming up to achieve the high end design concept.