Sector
Education
Price
£230k
Duration
12 Weeks

Redevelopment of classrooms to 3 Science Laboratories


As part of their golden jubilee celebrations, Beaconsfield High School contracted GPF Lewis to convert the existing woodworking and metalworking rooms into 3 new Science Laboratories. 

The 12 week schedule of works included demolition of the existing rooms, alterations to the existing layouts, installation of new Fresh Water Altro Flooring as well as mechanical & electrical installation and complete redecoration throughout.

"I was shown round the labs at Beaconsfield High today. The labs looked fantastic and the school is clearly delighted with the outcome of the project. Thank you for all your efforts, and well done."  Janet Johns, Bucks CC