This project inclued the constructiion of an extension to the existing building to provide two additional floors at roof level creating a fourth and fifth floor, containing 20 residential units. The works also comprised of the installation of a new passenger lift serving ground to fifth floor and a new staircase between the existing building and the proposed extension.  Internally the final finishes are being applied ready for tenants to move in on the 17th December. Externally the Cladding, Terraces and Green Roof are due to complete in the next two weeks.
 

We are looking forward to seeing the completion photos soon!